Burlington Is Replacing the 15-Year-Old Mountainside Splash Pad
The splash pad at Mountainside Recreation Centre is being replaced, and the city has scheduled the work so families do not lose a summer over it.
The pad at 2205 Mount Forest Drive went in beside the outdoor pool in 2011, and at 15 years old it is near the end of its life. Burlington has a tender out for an architect to design the replacement. That tender closes on November 27 and the city expects to award it before the end of the year.
Construction starts once the splash pad and the connected outdoor pool close for the winter in September 2027, and the work is due to finish by April 2028 so the pad can reopen for the summer. The new one gets low flow spray features to cut water use, and the underground piping and electrical already in the ground will be reused where that is possible.
The money was approved in the city's 2025 capital budget: $700,000 for the splash pad, inside a $1.75-million allocation for recreation and community centre repair and renewal. The replacement was first meant to be finished in spring 2026. City staff did not say what held it up.
Nothing beyond regular maintenance has been done to the pad since it was built. It also sat untouched through the two-year pool revitalization that closed the facility from September 2021 until June 2023, and because it runs on its own water system, it can stay open on days the main pool is shut.
The timeline
Design tender closes November 27, 2026 and is awarded by year end. Construction begins when the pad closes in September 2027. The new splash pad is due to open for summer 2028.